Week 9 in Review

Tasks Accomplished

This week the entire team met to finish activities done in class and further familiarize and develop a plan for the project.

Week 9 Tasks

Continue progress on architectural specification. Have a rough rough rough draft complete.

Challenges

These week many team members had a lot of work to do, so we couldn't get as much done as we would have liked.

Sunday, October 18, 2015

Week 8 in Review

Tasks Accomplished

This week we decided on a new project to take into the architecture phase, ScoreStream. During this week we decided on a project, created a new project plan to use for the architecture portion, and started filling out our software architecture document. Mike, Wayne, Damas, and Jeremy participated in this.

Week 9 Tasks

This next week we will continue familiarizing ourselves with the finer details of the project, and begin the first steps to making an architecture.

Challenges

We did not face any challenges this week.

Sunday, October 11, 2015

Week 7 in Review

Tasks Accomplished

This week we completed our requirements engineering process for the project. More specifically, this week we focused on writing use cases. We also met with our sponsor to verify our requirements specification one last time before our requirements presentation. All team members took part in completing use cases, descriptions, class diagrams, and sequence diagrams. Damas, Mike, Wayne, and Jeremy met with our sponsor to verify Requirements. Mike wrote the blog.

Week 8 Tasks

This next week we will decide on whether or not to continue with this project into the architecture phase, or pick up a new project with predefined software requirements. We will then begin the initial steps of the architecture phase.

Challenges

Our big challenge this week was illness among group members. However, we all survived and managed to complete the work.

Sunday, October 4, 2015

Week 6 in Review

Tasks Accomplished

This week we completed additional work towards the SRS. Wayne worked on implementing feedback from the SRS Draft, adding Actor Descriptions to the Use Case document, and adding more detailed use case descriptions. Mike worked on adding use cases for the Reference Materials package. Drew and Jeremy worked on adding use cases for the website management package. Lastly, Damas worked on adding use cases for the Cadet Tracking package.

Week 7 Tasks

Finalize the SRS document and supporting Use Cases.

Challenges

Our main challenge this week was finding the time to meet, and complete work because of the extra time taken up by the career fair and interviews for various team members.