Tasks Accomplished

This week we completed additional work towards the SRS. Wayne worked on implementing feedback from the SRS Draft, adding Actor Descriptions to the Use Case document, and adding more detailed use case descriptions. Mike worked on adding use cases for the Reference Materials package. Drew and Jeremy worked on adding use cases for the website management package. Lastly, Damas worked on adding use cases for the Cadet Tracking package.

Week 7 Tasks

Finalize the SRS document and supporting Use Cases.

Challenges

Our main challenge this week was finding the time to meet, and complete work because of the extra time taken up by the career fair and interviews for various team members.