Tasks Accomplished
This week we successfully completed our first draft of our Software Requirements Specification document. Additionally, we conducted an interview of our stakeholder and reviewed our Vision and Scope and SRS documents with them to ensure we were on the right track. Mike and Wayne conducted the majority of the interview -Jeremy joined in for the second half of it. In the SRS, Wayne worked on sections 3 and 6, Mike worked on sections 1 and 4, Damas worked on section 5, Jeremy worked on section 2, and Drew helped on sub-section 1.1. Mike and Wayne reviewed the document and worked on the Use Cases and Stereotype class models. Mike and Damas worked on the sequence diagram, and Mike wrote the blog.
Week 6 Tasks
Modify the SRS draft based on feedback and finalize it for the deliverable.
Challenges
Our main challenge was completing the SRS draft before the deadline, and team communication.